Landslide Markovici

Landslide Markovici

Having in mind the importance of the main road direction Cetinje-Budva, as well as the upcoming tourist season, and the fact that occurrence of the landslide in Markovici has caused traffic difficulties and influenced on the normal traffic on this very frequent roadway, Bemax company has decided to execute works on the rehabilitation of the landslide as the donation in the highest public interest.

Execution of the above mentioned works will be done in two phases. The works of first phases include the rehabilitation of the road, while the second phase is related to the construction of the drainage on the slope and reconstruction of the local road in Markovici.

After the earthworks, which include the preparation for the construction of piles, the production of pile structure will begin, which includes 332 of the pile, a length of 12 to 18 meters and a diameter of 1 to 1.2 meters, while the total pile network construction is over 5 kilometers.

The completion of the first phase works is expected by 30. June 2015., until when the traffic will be done trough one line, and during the execution of the second phase the traffic will be normally take place.

Other