Road Infrastructure
Reconstruction of the road Part: Pavino Polje-Kovren

Pljevlja
Reconstruction of the road Part: Pavino Polje-Kovren
Reconstruction of the road Part: Pavino Polje-Kovren
Reconstruction of the road Part: Pavino Polje-Kovren

Name and place of the facility:
Reconstruction of the road Slijepač bridge-Tomaševo-Pljevlja
Part: Pavino Polje- Kovren

Execution of preparation works, works on excavations and embankments, construction of lower support layer, building of reinforced-concrete plate, casket and pipe drainage holes, reinforced-concrete retaining walls, asphalt works on objects, observation of objects and ground.

Investor:
Crnagoraput a.d. Podgorica

The total investment value:
1.821.769,28 €

The year of construction:
2013 - 2014.

Reconstruction of regional road R-10, Part: Tomaševo - Pavino Polje
Tomaševo
Reconstruction of regional road R-10, Part: Tomaševo - Pavino Polje
Reconstruction of regional road R-10, Part: Tomaševo - Pavino Polje
Reconstruction of regional road R-10, Part: Tomaševo - Pavino Polje

Project Description:
Reconstruction of regional road R-10P
Part: Tomaševo-Pavino Polje, from km 11+040 to km 22+380

Making of execution design, execution of preparation works, works on the lower and top layer that involve excavation of all categories material of 65.866,56 m3 and works on embankment of all material categories making of 35.139,58 m3, bridge building, drainage holes and walls, setting of traffic signaling and road equipment, and all geodetic works. Length of the road part on which the works were executed is L=11,34 km.

Investor:
Government of Montenegro
Directorate of traffic

The total investment value:
3.076.634,92 €

The year of construction:
2010 - 2011.

Works on building of highway Risan-Žabljak
Žabljak
Works on building of highway Risan-Žabljak
Works on building of highway Risan-Žabljak
Works on building of highway Risan-Žabljak

Project Description:
Works on building of highway Risan-Žabljak,
Part: entrance in tunnel Ivica-Motički Gaj (km 3+090.50 - km 16+683.17)

Works on construction of highway and tunnel (L=2,2km). This project included works on excavation of material from third to sixth category (362.780,79 m3), making of embankments of all category materials (321.012,12 m3), making of bed, execution of concrete and reinforced-concrete works, setting of roadsides, horizontal and vertical traffic signaling and road equipment, hydro technical and electro-installation works, geodetic works. Length of road on which works were executed is L=13,60 km.

Investor:
Government of Montenegro
Directorate of traffic

The total investment value:
17.737.107,59 €

The year of construction:
2008 - 2011.